On November 24, U.S. Bitcoin miner CleanSpark released its fiscal 2026 results for the year ended September 30, 2026.

The numbers were grim: a net loss of $987.1 million for the year.

Data from The Block shows that it posted net income of about $365 million the previous year.

CleanSpark went from a profit last year to a loss of nearly $1 billion this year, a swing of more than $1.3 billion.

About 60% of the $987.1 million loss, however, did not represent cash outflows. It came from accounting adjustments to CleanSpark's Bitcoin holdings: a $281.6 million mark-to-market loss, a $177.2 million impairment charge and a $118.7 million collateral loss, totaling $577.4 million. On the company's own adjusted basis, full-year EBITDA was negative $304.2 million.

But the figure drawing the most attention in the earnings report was not the loss. It was $6.6 billion.

That is the value of a 20-year contract CleanSpark signed in July.

The company plans to turn its land and power assets into data centers that it can lease to AI customers.

How does a Bitcoin miner become an AI landlord? The answer starts with the economics of its crypto mining business.

Crypto Mining Economics Keep Getting Worse

CleanSpark generated $576.5 million in revenue in fiscal 2026, down 25% from the previous year.

Half of the decline came from mining fewer coins, and the other half from lower Bitcoin prices.

The company mined 7,253 Bitcoin during the year, 8% fewer than a year earlier. Its average computing power also fell 21% to 36.0 EH/s.

But with Bitcoin production down just 8% and revenue down 25%, the remaining 17 percentage points came from pricing. Dividing revenue by the number of coins mined yields an average of about $79,500 per Bitcoin in fiscal 2026, compared with roughly $97,200 the previous year. That decline closely matches the drop in revenue.

Computing power can be thought of as the combined horsepower of every mining rig at a mining farm. Less horsepower generally means fewer coins mined.

The Bitcoin halving had already laid the groundwork for the squeeze.

Under Bitcoin's rules, crypto mining rewards are cut in half roughly every four years. The most recent halving took place in April 2024.

Its impact is not confined to a single year's comparison. It reduces the long-term output from each unit of computing power: the same electricity and the same machines produce half as many coins, while power and equipment costs remain unchanged.

That is a challenge for the entire industry, not just CleanSpark.

There was some better news.

In the fourth quarter, from July through September 2026, revenue fell 46% year over year to $120.9 million, but CleanSpark still posted a quarterly profit of $9.8 million.

Against a full-year loss of nearly $1 billion, however, that profit barely makes a dent.

As the path forward for crypto mining narrows, CleanSpark needs a new source of growth.

What other cards does it have to play?

Leasing Power for 20 Years

As of September 30, 2026, CleanSpark held 13,530 Bitcoin worth about $1.1 billion at that day's price. Together with $204.8 million in cash, that gave the company roughly $1.3 billion in readily available funds.

The $1.1 billion figure reflects Bitcoin's price at the end of September. The cryptocurrency later fell below $60,000, sharply reducing the value of those holdings to just over $800 million based on prices in late November.

That still represents a substantial balance sheet by mining industry standards.

But CleanSpark's power and land may ultimately be worth more than its Bitcoin.

Crypto mining consumes enormous amounts of electricity, prompting miners in recent years to secure grid connections, buy land and build energy infrastructure.

Power is also the resource AI data centers now lack most.

The assets miners already own align closely with the AI industry's needs.

CleanSpark's first major deal is in Sandersville, Georgia, where it signed a 20-year lease worth a total of $6.6 billion.

In simple terms, CleanSpark will build the data center and lease it to a customer for 20 years, collecting $6.6 billion over the life of the contract.

The agreement is also structured as a triple-net lease.

That means the tenant, in addition to paying rent, covers property taxes, insurance and routine maintenance, leaving the landlord with few of those ancillary expenses.

Building a data center requires substantial capital. Where will that money come from?

CleanSpark issued $2.276 billion in senior secured notes.

In plain terms, the company borrowed against its assets. If it cannot repay the debt, these creditors stand first in line to recover their money.

The notes carry a 7.875% annual coupon and mature in 2031.

With the financing in place, the project's construction costs are now fully funded.

CleanSpark said it aims to deliver the first data hall in November 2027, with construction and spending currently on schedule.

The speed with which CleanSpark raised more than $2 billion suggests that capital markets have confidence in the project.

But the economics need to be unpacked.

The $6.6 billion is spread across 20 years, averaging just over $300 million annually.

That revenue will only begin arriving after the project is delivered in November 2027, assuming construction finishes on time and the customer pays as agreed.

At signing, the immediate addition to CleanSpark's balance sheet was interest-bearing debt.

How much interest? At 7.875% on $2.276 billion, the annual bill comes to about $180 million.

For comparison, CleanSpark generated only $576.5 million in total revenue in fiscal 2026. The annual interest on this debt alone is equivalent to nearly one-third of that figure.

If the project is delivered six months late, the interest still has to be paid during that delay.

The project's success therefore hinges on one issue: whether power becomes available on schedule.

Approval Does Not Mean Availability

CleanSpark has another major pool of power assets in Texas.

There, it controls a power portfolio of up to 885 MW, including 585 MW that has received "Conditional Batch Zero" baseload status.

The terminology is arcane. Batch Zero can be understood as the first group of large power users in line for a grid connection in Texas, while baseload refers to stable, round-the-clock power.

That status puts CleanSpark near the front of the interconnection queue.

But the word "Conditional" matters. The status only becomes valid once certain requirements are met, and it has not yet been fully finalized.

Meanwhile, exclusivity periods for CleanSpark's Sealy and Brazoria projects in Texas expired before the regulatory picture became clear.

An exclusivity period is a window during which the resource is reserved for negotiations with one party and others cannot step in.

Now that those lock-up periods have ended, CleanSpark has less control over the two projects.

Industry insiders know that several hurdles remain between securing power approval and collecting rent:

grid approval, data hall construction, grid interconnection and customer inspection and occupancy.

A delay at any stage could push back the November 2027 target.

The market is doing the same math.

On Tuesday, November 24, CleanSpark shares closed at $5.115, down 7.5% for the day. The stock had already been falling before the earnings release.

The investor reaction suggests that the market is more focused on the company's immediate, tangible losses, while revenue from the AI business will not begin materializing until after November 2027.

CleanSpark is not alone. A number of Bitcoin miners are pivoting in the same direction.

The logic is straightforward: the halving has squeezed crypto mining margins, AI has made power more valuable, and miners already control grid connections, land and energy infrastructure.

The appeal is clear. A miner's earnings once depended largely on Bitcoin's price, with revenue falling whenever the cryptocurrency declined.

A rental model, especially under a triple-net lease, should produce much steadier annual revenue and look more like a conventional property business.

But the risks have merely changed form.

Instead of worrying only about Bitcoin prices, CleanSpark must now consider whether construction will finish on time, whether it can withstand the interest burden, and whether AI companies will still be investing aggressively after 2027. For now, it has exposure on both sides:

On one side are 13,530 Bitcoin, worth $1.1 billion at the end of September but only a little over $800 million at current prices. Another 10% drop in Bitcoin would erase more than $80 million in book value.

On the other side is $2.276 billion of debt, with interest payments due on schedule.

For miners, power is replacing mining rigs as their most valuable asset.

Delivering the first Sandersville data hall on schedule in November 2027 will be the first major test of the $6.6 billion lease.

Only then will the market be able to judge whether this crypto mining company can succeed as an AI landlord.