Power is the unavoidable issue in data centers this year. In the 2026 wave of AI infrastructure investment, the two most discussed topics are capital expenditure and electricity. Several hyperscalers have raised their spending plans again, rack densities have climbed from just over 10 kW to more than 100 kW, and liquid cooling has become the default. Globally, more projects under construction are stuck in grid-connection queues than held up by land. Southeast Asia is following the same pattern: Indonesia is racing to secure power, while Thailand is waiting in line.
Power Comes First, Construction Follows
The timeline tells the story. On April 17, DayOne signed a 511 MVA power purchase agreement with PLN Batam, the largest data center power deal yet in Indonesia. In October, China Construction Third Engineering Bureau and Lintuo Technology signed a cooperation framework in Wuhan for a 1.6 GW project in Purwakarta.
In Thailand, the Board of Investment approved six projects worth 958 billion baht in a single batch on May 6. By August, Caixin reported that 10 GW of data center capacity was waiting for power.
Three Locations, 13 Projects
About 50 kilometers east of Jakarta lies Bekasi’s industrial belt. Batam is the other hub, an island in the Riau Archipelago across the water. Bangkok-area projects are spread across Samut Prakan, Chachoengsao and Chonburi. Across these three areas, 13 projects under construction or expansion have enough publicly available details to track: eight in Indonesia and five in Thailand.
Batam has 0.9 GW of installed generation capacity, while its operating data centers account for just 70 MW. DayOne alone has contracted 511 MVA — more than half of the island’s installed generation capacity when both are compared on contracted capacity. Thailand has the opposite problem: approvals were granted in one sweep, but projects face waits of nearly two years for power allocations.
Sources include the official newsrooms of owners and contractors, including DayOne, Bridge, STT/NeutraDC, Digital Edge, PDG and Empyrion; local approval records from Thailand’s Board of Investment, the BP Batam website and Indonesia’s Investment Coordinating Board; and institutional data from Cushman & Wakefield, BMI and DC Atlas, cross-checked against on-the-ground reporting from Caixin, Reuters and others.
Chinese Players Have a Role in Six of the 13 Projects
Of the 13 projects, four involve Chinese capital or operators, one has a Chinese EPC framework, and one is located in a Chinese-backed industrial park but operated by a foreign company. None involves Chinese equipment suppliers. In Indonesia, capital moved in first; in Thailand, demand came first. Those different sequences have shaped the roles Chinese companies play.
Power, Water and Approvals
Power is the shared constraint across all three locations. Batam has 0.9 GW of installed generation capacity, 70 MW of operating data centers and a 747 MW development pipeline. At full load, demand would reach roughly 1 GW, already exceeding existing capacity. Because Batam has an isolated grid, a shortfall cannot be covered by Indonesia’s main power network.
Thailand’s numbers are even more direct: at least 10 GW of data center capacity is waiting for power allocations, with approvals taking nearly two years.
Water is starting to appear in contracts. Bridge signed a 10-year supply agreement with Eastwater for its Chonburi operations, capped at 3.3 million cubic meters a year, or about 9,000 cubic meters a day. Data center water consumption once stayed off financial statements; it is now being written into long-term agreements.
The pace of approvals determines the pace of construction. Thailand’s Eastern Economic Corridor plans to add 1,150 MW of power capacity. Of that, 400 MW is already operating and the remaining 750 MW is under construction. Indonesia issues approvals relatively quickly, but its bottleneck is the grid. A 10-year PPA in Batam effectively locks up power supply for the coming decade.
A Tale of Two Markets: 23% Versus 0.7%
Another pair of figures readers will ask about is vacancy and rent. Bangkok and its surrounding areas have 134 MW in operation and a vacancy rate of about 23%, compared with 0.7% in Johor and roughly 4.9% in Singapore.
High vacancy gives tenants bargaining power. Most new Thai projects therefore come with demand already attached: TikTok, Bridge and Skyline are building only after securing customers or identifying internal group demand. Purely speculative third-party data center campuses are difficult to make work in Bangkok. Johor is the opposite. A 0.7% vacancy rate means operators have little trouble finding tenants, while prices can still be set at one-third to one-half of Singapore’s levels.
Indonesia secures power first, Batam builds facilities before finding customers, and Thailand brings in demand before construction. The three sequences create three distinct market positions.
A Framework Is Not an Order
Indonesia has secured a gigawatt-scale framework: the 1.6 GW Purwakarta project, signed in Wuhan in October 2026, with China Construction Third Engineering Bureau serving as EPC contractor. But a framework is not an order. The formal contract covers only the initial 50 MW phase. The supporting 6,870-kilometer SGI subsea cable is not due until 2028; without it, there is no clear route for external bandwidth.
Thailand still has no Chinese-led third-party data center. TikTok is its own project owner. Bridge’s Thai platform is building campuses and expanding existing facilities in response to demand, with Chinese involvement focused on operations and mechanical and electrical systems rather than capital. Data centers built by Chinese internet companies form a separate track. Alibaba Cloud opened a public cloud region in Johor in June, bringing its total in Malaysia to five. ByteDance’s three-location deployment in Thailand has already received Board of Investment approval. Procurement decisions for both companies are made at headquarters, not by local project teams.
Local colocation providers are adding renewable power. ETIX BKK#1 in Bangkok has an IT load of only 5 MW, but its roof is blanketed with solar panels. Its customers include banks, OTT platforms and cloud service providers. Small and midsize facilities seek premiums through renewable power and connectivity, a different business model from hyperscale campuses.
Next year’s growth in the region will hinge on three developments: phases two and three of Indonesia’s GIIC project, Batam’s second PPA, and when the remaining 750 MW in Thailand’s Eastern Economic Corridor comes online. Only when the power arrives can approvals turn into construction sites.