As AI data center construction gathers pace, the mechanical and electrical engineering that powers and cools these facilities is also drawing attention. An order worth hundreds of millions of yuan is often seen as proof that an engineering company has caught the AI investment wave. But a shift more consequential than the size of these contracts is now changing how the business is done.

In a November 3, 2026 announcement of preferred bidders for the EPC contract covering the B1 and C1a buildings in Phase 2.1 of China Telecom’s Lingang Information Park Phase II, a consortium comprising Shanghai Telecom Engineering Co., Shanghai Post and Telecommunications Design Consulting Institute Co., and China Construction Fifth Engineering Bureau ranked first. Its tax-inclusive bid was about 506 million yuan. The buyer was Lingang Computing Power (Shanghai) Technology Co., and the contract followed the EPC model, placing design, procurement and construction under a single contractor.

Equipment accounted for about 427 million yuan, or 84.5%, of the bid. That shows equipment procurement is a major part of the project. But the bid itself does not reveal how much the consortium could earn or how the proceeds would be divided among equipment suppliers.

The more important question is this: As more of this equipment is assembled into complete modules at factories, how much responsibility will engineering companies retain in front of the customer? Recent moves by Chinese and international vendors are changing the answer.

Equipment Is Being Sold Differently

Power supplies, cooling equipment, cables and control systems in a data center must work together. When they are procured separately, equipment from different suppliers still has to be connected on-site, requiring coordination across design, installation and commissioning. Part of an EPC contractor’s value lies in organizing that work.

Now, some of that coordination is being built into the product before it reaches the site.

On November 19, Guangdong Headway Technology Co., which specializes in data-center thermal management and other systems, unveiled a 5 MW prefabricated solution. The 5 MW figure refers to the designed power load of the computing equipment. According to the company’s November 23 description, the solution integrates cooling, power, IT and supporting systems in a unified design, with more preinstallation, integration and testing completed at the factory before assembly on-site. This was the launch of a new solution and should not be treated as evidence that a batch of such data centers is already in operation.

Similar moves are underway overseas. On October 21, power distribution and energy-management company Schneider Electric introduced a modular data center reference design for NVIDIA’s Vera Rubin computing platform. It brings power, liquid cooling, space for computing equipment, software and ongoing services into a single design. A reference design serves as a reusable construction blueprint, though customers must still adapt and implement it for individual projects.

Vertiv’s OneCore product extends the scope to the building itself. Its website describes a delivery model in which Vertiv handles the entire facility above the foundation, including the data halls that house computing equipment.

What these companies want customers to buy now goes beyond a single air conditioner or power system. Module suppliers are beginning to take responsibility for coordinating equipment, carrying out some installation work and organizing delivery. For them, each customer can buy a broader range of products and services. For companies that previously handled item-by-item procurement and on-site integration, some of that work now has a new provider.

Equipment accounting for 80% of an engineering bid therefore does not automatically mean equipment vendors capture 80% of the profit. The more important questions are who combines the equipment, who explains the trade-offs to the customer, and who takes responsibility for delivering the integrated system. Even with the same procurement value, companies can occupy very different positions in the transaction.

Why the Shift Is Accelerating Now

Prefabrication was not invented by the AI boom.

An article published by ZTE in its own technical journal in 2021 described moving data-center equipment assembly into the factory. According to the company, the first four data-hall modules in a project for an internet customer were completed in July 2020, passed preliminary acceptance and were handed over for use. The participants included design, product and construction teams, while the assignment remained an MEP EPC contract.

That history is a reminder not to repackage an established construction method as an industry revolution that suddenly appeared this year. What matters is the problem prefabrication is now being used to solve and who is providing it.

Schneider’s new design directly addresses a new generation of computing platforms, while Headway has also built support for different generations of computing power architectures into its solution. The power and cooling requirements of high-density computing equipment are increasingly considered alongside the data center itself during the design phase. As a result, equipment selection, spatial layout and installation planning are harder to handle independently and piece together at the end.

Reducing on-site coordination has tangible value. A campus study jointly disclosed by Schneider Electric and data center developer Compass found that on-site installation time for a prefabricated data-hall module fell from 75.5 hours to 15 hours. The two companies jointly designed the module, integrating previously separate systems into a single assembly unit.

That result covers only the on-site installation of the module studied. It does not mean construction time for an entire data center was cut by 80%, much less that 80% of the workforce could be eliminated. A significant share of the work was simply moved upstream to the factory.

Still, it shows why customers are changing how they buy. Every instance of waiting between different trades that can be removed from the site eliminates one more step requiring ad hoc coordination. Companies that resolve these dependencies in advance have an opportunity to enter customer discussions earlier. If engineering companies do not become involved until the equipment list and module design have been finalized, they will naturally have fewer choices and fewer opportunities to make adjustments.

Seen this way, competition does not begin only in the final bidding round. Once customers decide which systems to procure together, part of the division of responsibilities is already taking shape.

How Engineering Contractors Will Diverge

Does this mean equipment vendors will squeeze engineering contractors out? The available evidence does not support such a simple conclusion.

Vertiv’s OneCore also offers another model: the customer or EPC contractor provides the building, while Vertiv supplies the modules. Its product documentation explicitly preserves a role for the EPC contractor. Schneider’s installation study also came from a joint design effort with a developer, while ZTE’s earlier project had product and construction teams jointly carrying out the EPC assignment. None of these partnerships treats manufacturing and engineering as a zero-sum business in which only one side can survive.

The more likely dividing line is whether a company can continue participating in the customer’s overall decision-making.

Teams that only procure from a list and perform repetitive installation face direct pressure: customers can purchase some of that work as part of a module. Engineering teams that can contribute to early-stage design, determine whether a module suits a project, and coordinate on-site connection and acceptance still have work to do. Two companies may both be called EPC contractors while possessing very different capabilities.

The shift will also reach smaller equipment suppliers. Previously, the goal was to win a procurement order for a particular project. When equipment is first incorporated into modules that can be delivered repeatedly, securing selection by a module manufacturer becomes another important objective. A place in a standardized configuration could lead to supply opportunities across multiple projects; failing to make the cut could mean missing the selection process for an entire group of projects. Whether that outcome materializes will still depend on customer adoption and whether the modules can be reused. Inclusion in a solution should not be equated with having already secured an order.

Developers must also make new trade-offs. Integrated modules can reduce the number of tasks they need to coordinate, but they place more concentrated demands on the module supplier’s design, delivery and ongoing service capabilities. Keeping procurement separate means the developer or EPC contractor must continue managing more of the interfaces. Vendors currently offer both approaches, and there is no evidence that all customers are choosing the same one.

Against this backdrop, the roughly 500 million yuan MEP bid for the Lingang project shows how one project was tendered. The contract value alone cannot indicate how much engineering companies will benefit over the long term, nor can overseas product designs be used to infer what equipment the project will adopt. Taken together, however, evidence from different markets points to a competitive shift worth watching: equipment companies are taking on more engineering coordination, while engineering companies must redefine which customer problems they can solve.

AI data center construction still requires people to connect equipment, buildings and real-world operations. Prefabrication makes some of that work repeatable in a factory, while forcing companies to renegotiate their respective responsibilities. For engineering contractors, their position in the next round of orders will depend on the work they actually perform as solutions take shape and are delivered. Looking only at the EPC roster is likely to obscure how the business is changing.